Batang Rambungan Bridge contractor urged to solve cash flow issues,

KUCHING: The contractor building the RM98.5 million Batang Rambungan Bridge here has been told to solve its cash flow and workers problems soonest. Deputy Premier Datuk Amar Douglas Uggah said the project was supposed to be completed on December 16 this year. However, he said, it has been revised to June 23 next year. “Its […]

Bridge completion date revised

Batang Rambungan Bridge

KUCHING: The revised expected completion date of the iconic Batang Rambungan Bridge project is March 31, 2023. Assistant Infrastructure and Ports Development Minister Datuk Julaihi Narawi said that the project’s progress thus far is at 11 percent (compared to the schedule’s 32.7 percent). In saying this, he noted that the project still qualifies for time […]