Security personnel to report at new airport

MUKAH: The new Mukah Airport costing RM435.9 million at KM7, Jalan Mukah-Oya here is expected to be operational before this coming Gawai Dayak. Meanwhile, work is in progress to complete the airport in order to finish in time to host the first and historic flight. It was reported recently that security personnel will report for […]

New Mukah Airport operational next month

MUKAH: The new RM302.4 million Mukah Airport is 90 percent completed in January this year. Now, final maintenance work is being carried out before the airport begins operation next month. Tellian assemblyman Yussibnosh Balo told Suara Sarawak here today that initially, work on the project was delayed for three months due to the implementation of […]

Coastal highway U-Turn poses danger to users

MUKAH: The construction of a U-Turn at the KM7 Mukah-Oya highway supposed to facilitate traffic flow near the new Mukah Airport has led to somewhat dubious circumstances. New Sarawak Tribune observed that while the U-Turn has a significant purpose for being constructed at that section of the coastal highway, it lacked safety aspects that should […]

New Mukah Airport to operate next year

MUKAH: The new Mukah Airport costing RM435.9 million at KM7, Jalan Mukah-Oya here will be operational in the second quarter of next year. This is after the completion date of the ongoing project that has been revised from Jan 2 to April 11, 2021. Tellian assemblyman Yussibnosh Balo said the project had been scheduled to […]

Mukah Airport to be completed by January

MUKAH: The much-awaited RM302.4 million new Mukah Airport is scheduled for completion by Jan next year. Tellian assemblyman Yussibnosh Balo said works on the project have been disrupted for at least three months earlier this year due to the implementation of the movement control order (MCO) to curb the spread of Covid-19. “However, construction work […]

New Mukah airport ready next Jan

MUKAH: The construction of the new RM360-million Mukah airport is expected to be completed by January next year. Deputy Chief Minister Tan Sri Datuk Amar Dr James Jemut Masing said the construction work had been disrupted for three months due to the movement control order (MCO). “Now work has started again,” he told a press […]